October 2021 Update Summary

Wylie East High School Additions & Renovations

  • Area A Storm Shelter/Gym Building Exterior Masonry Complete. Locker and Shower Rooms have been turned over for use. Gym Floor is complete. Still work to do with Audio Visual and punch for the Arena Area. Working on exterior Canopies and Landscaping.

    • Area L is complete and turned over for use. Punch items are still pending.
    • Area M is complete and turned over for use. Punch items are still pending.
    • Area R has been turned over for use. Dust collectors are currently being installed, as well as, added electrical.
    • Areas D and F are complete and turned over for use. Punch items still pending.
    • Areas Q, S, and F have been turned over for use. Punch items still pending.
    Wylie East High School Bond Construction Photo.  East side area. Wylie East High School Bond Construction Photo.  North East side area. Wylie East High School Bond Construction Photo.  South West side area. Wylie East High School Bond Construction Photo.  East Cafeteria area.

Wylie High School Additions & Renovations

  • The project is complete.

    Wylie High School Bond Construction Photo. South East side area.Wylie High School Bond Construction Photo. South East side area closer. Wylie High School Bond Construction Photo. South East aerial closer. Wylie High School Bond Construction Photo. South East aerial.Wylie High School Bond Construction Photo. South East aerial.Wylie High School Bond Construction Photo. South East aerial.

Bush Elementary Additions & Renovations

  • The project is complete.

    Wylie High School Bond Construction Photo. South East side area.Wylie High School Bond Construction Photo. South East side area closer. Wylie High School Bond Construction Photo. South East aerial closer. Wylie High School Bond Construction Photo. South East aerial.Wylie High School Bond Construction Photo. South East aerial.Wylie High School Bond Construction Photo. South East aerial.

Cox Elementary Additions & Renovations

  • The project is complete.

    Wylie High School Bond Construction Photo. South East side area.Wylie High School Bond Construction Photo. South East side area closer. Wylie High School Bond Construction Photo. South East aerial closer. Wylie High School Bond Construction Photo. South East aerial.Wylie High School Bond Construction Photo. South East aerial.Wylie High School Bond Construction Photo. South East aerial.

Watkins Elementary Additions & Renovations

  • The project is complete.

    Wylie High School Bond Construction Photo. South East side area.Wylie High School Bond Construction Photo. South East side area closer. Wylie High School Bond Construction Photo. South East aerial closer. Wylie High School Bond Construction Photo. South East aerial.Wylie High School Bond Construction Photo. South East aerial.Wylie High School Bond Construction Photo. South East aerial.

Harrison Intermediate Additions & Renovations

  • The project is complete.

    Wylie High School Bond Construction Photo. South East side area.Wylie High School Bond Construction Photo. South East side area closer. Wylie High School Bond Construction Photo. South East aerial closer. Wylie High School Bond Construction Photo. South East aerial.Wylie High School Bond Construction Photo. South East aerial.Wylie High School Bond Construction Photo. South East aerial.

Groves Elementary Additions & Renovations

  • The project is complete.

    Wylie High School Bond Construction Photo. South East side area.Wylie High School Bond Construction Photo. South East side area closer. Wylie High School Bond Construction Photo. South East aerial closer. Wylie High School Bond Construction Photo. South East aerial.Wylie High School Bond Construction Photo. South East aerial.Wylie High School Bond Construction Photo. South East aerial.

Whitt Elementary Additions & Renovations

  • The project is complete.

    Wylie High School Bond Construction Photo. South East side area.Wylie High School Bond Construction Photo. South East side area closer. Wylie High School Bond Construction Photo. South East aerial closer. Wylie High School Bond Construction Photo. South East aerial.Wylie High School Bond Construction Photo. South East aerial.Wylie High School Bond Construction Photo. South East aerial.

Davis Intermediate Additions & Renovations

  • Building turned over for use.

    Wylie High School Bond Construction Photo. South East side area.Wylie High School Bond Construction Photo. South East side area closer. Wylie High School Bond Construction Photo. South East aerial closer. Wylie High School Bond Construction Photo. South East aerial.Wylie High School Bond Construction Photo. South East aerial.Wylie High School Bond Construction Photo. South East aerial.

McMillan Junior High Additions and Renovations

  • Building turned over for use.

    Wylie High School Bond Construction Photo. South East side area.Wylie High School Bond Construction Photo. South East side area closer. Wylie High School Bond Construction Photo. South East aerial closer. Wylie High School Bond Construction Photo. South East aerial.Wylie High School Bond Construction Photo. South East aerial.Wylie High School Bond Construction Photo. South East aerial.

Dodd Elementary Additions and Renovations

  • Started Project October the 4th. Excavation for Crawlspace is complete. Started Drilling Piers October 31st. Will start Grade Beams 1st of November. Grade Beams should be complete by mid-November. Storm Shelter Concrete Walls will start soon after.

    Wylie High School Bond Construction Photo. South East side area.Wylie High School Bond Construction Photo. South East side area closer. Wylie High School Bond Construction Photo. South East aerial closer. Wylie High School Bond Construction Photo. South East aerial.