April 2021 Update Summary

Wylie East High School Additions & Renovations

  • Area A Storm Shelter/Gym Building Exterior Masonry ongoing. High Ceiling work Overhead MEP and Low Voltage is complete. Dry Fall is complete. Clouds on concourse level are complete. Area L Exterior Masonry is complete. Framing Storefront at Entry is complete. Tilework is complete. Millwork is nearly complete. Building should be turned over to district by end of May. Area M Ceiling grid installed. Paint is complete. Flooring is ongoing. Building should be turned over by 1st of June. Area R and U Masonry CMU is complete. MEP rough in is ongoing and nearly complete. Painting has begun. Tile work is ongoing in both areas. Area D and F Drywall Framing is complete. MEP Overhead is complete 1st Floor and nearly complete on 2nd Floor. Ceiling grid installation has begun. Exterior masonry will begin 1st of May.

    Wylie East High School Bond Construction Photo.  East side area. Wylie East High School Bond Construction Photo.  North East side area. Wylie East High School Bond Construction Photo.  South West side area. Wylie East High School Bond Construction Photo.  East Cafeteria area.

Wylie High School Additions & Renovations

  • Area J Handrail in Gym is ongoing. Glass Entry Frame will finish by mid-May. Metal Panels are complete. Tilework in Stairwells is ongoing. Projector Screen is installed. Area D Painting in Cafeteria is ongoing. Tectum Panel installation is complete. Light fixtures in Cafeteria is ongoing. Area K and L Tilework in 2nd level Corridor is ongoing. MEP trim out is ongoing. Ceiling Grid has started. Millwork in K is ongoing. Area Q and R Steel Erection is ongoing. Area Q Interior and Exterior CMU ongoing. Plumbing wall rough is ongoing. CMU work continues. Plumbing rough is ongoing. Ductwork installation is ongoing.

    Wylie High School Bond Construction Photo. South East side area.Wylie High School Bond Construction Photo. South East side area closer. Wylie High School Bond Construction Photo. South East aerial closer. Wylie High School Bond Construction Photo. South East aerial.

Bush Elementary Additions & Renovations

  • Area A VCT Flooring nearly complete. Millwork nearly complete. Bathroom Ceramic Wall Tile nearly complete. Finish Trades and Low Voltage Ongoing. Courtyard Sod is complete. Classroom Lockers installed. Should walk Architectural Interior Punch by middle of May. Should walk Architectural Exterior and Civil Punch by 3rd week of May. Should turn Area A over to district by 1st of June. Area C work is complete working on punch list.

    Aerial photo of Bush Elementary School Aerial photo of Bush Elementary School Aerial photo of Bush Elementary School Aerial photo of Bush Elementary School

Cox Elementary Additions & Renovations

  • New Addition is complete. Architectural Punch is complete. Building turned over for use to district. Remaining renovations for existing building to begin this summer.

    Aerial photo of Cox Elementary School Aerial photo of Cox Elementary School Aerial photo of Cox Elementary School Aerial photo of Cox Elementary School

Watkins Elementary Additions & Renovations

  • Area A Cafeteria Expansion/Music Room completed and turned over to district. Fire Lane and Sidewalk concrete has been poured. Existing Music Room nearly complete. Exterior Masonry is complete. Area E Classrooms the Architectural punch has been done and contractor is working on completing punch items. Area E Storm Shelter Exterior Masonry is complete. All walls are painted. MEP Overhead is complete. Tape Bed and Paint is complete. Wall Tile is complete. Storm roll-up door installation is complete. Flatwork on exterior has been poured. Lockers and Millwork has been installed. Will walk Architectural Punch mid to late May. Gym in area A is nearing completion and will also walk Architectural Punch mid to late May.

    Aerial photo of Watkins Elementary School Aerial photo of Watkins Elementary School Aerial photo of Watkins Elementary School Aerial photo of Watkins Elementary School

Harrison Intermediate Additions & Renovations

  • Area A MEP work above ceilings is nearly complete. Fire Sprinkler Pipe complete. Masonry is complete. All HVAC units have been started with the exception of the kitchen. Ceiling Grid has started in some areas. Flooring in Restrooms has started. Area B all HVAC Units have been started. Flooring in Restrooms has started. Ceiling Grid Installed. Above Ceiling MEP Inspection done and approved. Permanent Exterior Doors will be installed by middle of May.

    Aerial photo of Harrison Intermediate School Aerial photo of Harrison Intermediate School Aerial photo of Harrison Intermediate School Aerial photo of Harrison Intermediate School

Groves Elementary Additions & Renovations

  • Exterior Brick Veneer is ongoing. Roofing is ongoing. Underground roof drain tie in has started. Interior Drywall framing complete. Tape and Bed has started. Low Voltage Cabling is ongoing. HVAC rough is ongoing. Installation of Tanks and Electrical Panels has started. Ceramic Wall Tile will start soon.

    Aerial photo of Groves Elementary School Aerial photo of Groves Elementary School Aerial photo of Groves Elementary School Aerial photo of Groves Elementary School

Whitt Elementary Additions & Renovations

  • Fire Alarm rough in the existing building is complete. Exterior Waterproofing complete. Masonry to start soon. Interior Drywall Framing is ongoing. MEP Overhead rough is ongoing. One siding Drywall is beginning early May. Sprinkler rough is ongoing. Electrical Panels are installed.

    Aerial photo of Whitt Elementary School Aerial photo of Whitt Elementary School Aerial photo of Whitt Elementary School Aerial photo of Whitt Elementary School

Davis Intermediate Additions & Renovations

  • Lightweight Concrete on Roof has been poured. Roof Curbs have been installed. Waterproofing exterior complete. Drywall Framing on 1st Floor and 2nd Floor complete. MEP Overhead started. Electrical Rough has started on the 1st and 2nd Floor nearly complete. Glazing Frames installed. Should start ceiling grid in May. Should be starting Tape Bed and Paint by the end of May.

    Aerial photo of Davis Intermediate School Aerial photo of Davis Intermediate School Aerial photo of Davis Intermediate School Aerial photo of Davis Intermediate School

McMillan Junior High Additions and Renovations

  • Roof Curbs set. Exterior Framing starting in May. 1st and 2nd Floor MEP Overhead Rough is ongoing. Interior Drywall Framing has started. Should finish Drywall Framing Mid May. MEP Overhead Rough should finish in late May. Exterior Sheathing and Waterproofing should be complete.

    Aerial photo of McMillan Junior High School Aerial photo of McMillan Junior High School Aerial photo of McMillan Junior High School Aerial photo of McMillan Junior High School