February 2021 Update Summary

Wylie East High School Additions & Renovations

  • Area A Storm Shelter/Gym Building Exterior Masonry ongoing. All windows installed. High Ceiling work overhead MEP and Low Voltage is almost complete Dry Fall will be starting soon. Lower Level MEP wall and ceiling rough in is ongoing. Area L Exterior Masonry is complete. Framing Storefront at Entry is complete. Paint ongoing 1st and 2nd Floors. Tilework ongoing. Area M Interior Masonry is complete. Framing for Drywall and MEP rough in is ongoing. Area R and U Steel Erection is complete with Masonry CMU nearly complete. MEP rough in is ongoing. Sheet Metal Roof Panel installation is ongoing. Area D 2nd Level Slab on Metal Deck is poured and Steel Erection almost complete.

    Wylie East High School Bond Construction Photo.  East side area. Wylie East High School Bond Construction Photo.  North East side area. Wylie East High School Bond Construction Photo.  South West side area. Wylie East High School Bond Construction Photo.  East Cafeteria area.

Wylie High School Additions & Renovations

  • Area J Exterior Damp Proofing and Masonry are ongoing. High Ceiling Clouds and MEP Trim Out is ongoing. Scaffolding coming down middle of March. Will finish Locker Rooms for Spring Break turnover. Area D Exterior Damp Proofing is ongoing. Tilework in Corridor is ongoing. Paint is ongoing. Glass install is almost complete. Area K and L Interior Framing is ongoing. Exterior Frames and Glass Installations are complete. Tilework in corridors is ongoing. MEP rough in ongoing. Sheet rock continues. Area Q Piers are complete. Grade Beams are complete. Electrical Underground work is complete. Area R Demo has started in the Weight Room.

    Wylie High School Bond Construction Photo. South East side area.Wylie High School Bond Construction Photo. South East side area closer. Wylie High School Bond Construction Photo. South East aerial closer. Wylie High School Bond Construction Photo. South East aerial.

Bush Elementary Additions & Renovations

  • Area A Exterior Brickwork is ongoing. Roofing is complete. 1st Floor Storefront Door Installation is complete. Tape Bed and Paint is ongoing. Hard Ceilings are Framed and Sheetrocked. 2nd Floor Plumbing Rough Complete. HVAC Ductwork was completed in early February. Electrical Rough in is complete. Fire Alarm Rough in completed. Area C work is complete working on punch list.

    Aerial photo of Bush Elementary School Aerial photo of Bush Elementary School Aerial photo of Bush Elementary School Aerial photo of Bush Elementary School

Cox Elementary Additions & Renovations

  • New Addition is complete. Architectural Punch is nearly complete. Building turned over for use. Remaining renovations for existing building to begin this summer.

    Aerial photo of Cox Elementary School Aerial photo of Cox Elementary School Aerial photo of Cox Elementary School Aerial photo of Cox Elementary School

Watkins Elementary Additions & Renovations

  • Area A Cafeteria Expansion/Music Room is nearly complete. Will walk punch on3-19-21. Firelane and Sidewalk concrete to be poured 3-19-21. Exterior Masonry is completed. Area E Classrooms is also nearing completion and is to be turned over after spring break. RTUs have been set on Area A and E Classrooms and flooring is near completion. MEP Trim out nearly complete. Area E Storm Shelter Exterior Masonry is complete with all that remains is over entry. All walls are framed. MEP Overhead is complete. Tape Bed and Paint ongoing. Wall Tile is nearly complete. Storm roll-up door installation is complete.

    Aerial photo of Watkins Elementary School Aerial photo of Watkins Elementary School Aerial photo of Watkins Elementary School Aerial photo of Watkins Elementary School

Harrison Intermediate Additions & Renovations

  • Area A MEP work above ceilings is ongoing. Interior fur downs framing in cafeteria are being painted. Fire Sprinkler pipe rough in is complete. Exterior Waterproofing is being applied ahead of mason. Exterior storefront glass is complete. Roofing is completed. Interior Masonry around columns is complete. Roof Top Units have been installed. Area B Exterior Masonry is complete. Installation of Storm Door Frames are complete. Installation of Transformers and Electrical Panels are set. Fire Sprinkler pipe rough in is complete. Drywall Ceilings and Fur downs work is ongoing.

    Aerial photo of Harrison Intermediate School Aerial photo of Harrison Intermediate School Aerial photo of Harrison Intermediate School Aerial photo of Harrison Intermediate School

Groves Elementary Additions & Renovations

  • Grade Beams are completed. Crawlspace has been graded. Waterproofing Grade Beams is complete. Installation of MEP in the Crawl Space ongoing. Structural Steel has begun in early February. 1st Floor has been poured. Structural Concrete Walls have been poured. Structural Steel for 2nd Floor will begin in early March.

    Aerial photo of Groves Elementary School Aerial photo of Groves Elementary School Aerial photo of Groves Elementary School Aerial photo of Groves Elementary School

Whitt Elementary Additions & Renovations

  • Fire Alarm rough in the existing building is ongoing. Grade Beam concrete is complete. Waterproofing the Grade Beams is complete. Grade Beam backfill is complete. Forming of structural concrete walls has begun and about half have been poured. Structural Steel has been delivered. Crawlspace has been graded. Structural Steel Erection to begin in early March.

    Aerial photo of Whitt Elementary School Aerial photo of Whitt Elementary School Aerial photo of Whitt Elementary School Aerial photo of Whitt Elementary School

Davis Intermediate Additions & Renovations

  • Structural Walls are complete. Crawl Space is graded out. MEP Rough In underfloor is ongoing. Structural Steel is nearly complete. 1st and 2nd Floor concrete has been poured.

    Aerial photo of Davis Intermediate School Aerial photo of Davis Intermediate School Aerial photo of Davis Intermediate School Aerial photo of Davis Intermediate School

McMillan Junior High Additions and Renovations

  • All utility work completed. Underground acid basin is installed and piped in. Grade Beams are complete. Waterproofing and backfill is complete. Concrete walls is complete. Steel Erection to begin in Early March.

    Aerial photo of McMillan Junior High School Aerial photo of McMillan Junior High School Aerial photo of McMillan Junior High School Aerial photo of McMillan Junior High School