October 2020 Update Summary
-
The information below is a summary of the work done to date. For more detailed information, please view our monthly bond update document. The file contains several charts that may not be accessible to screen readers. If you need assistance with this information, please contact Nathan Watson, Director of Construction Services.
Wylie East High School Additions & Renovations
-
Area A Storm Shelter/Gym Structural Steel is complete. MEP rough in continuing. Bleachers have been poured. Stairs are being installed. Benches in locker rooms have been poured. Exterior framing is ongoing. Area L Steel Erection is completed. MEP Rough In is near completion on the first floor. Installing Stairs now. Exterior Sheathing almost complete. Area M Interior Masonry is near completion. Roof Steel is almost completed. MEP Rough In is ongoing. Area R and U is ready for Steel Erection. Dug Outs the CMU is complete. Working on MEP rough ins. Benches have been poured. Area D Piers are drilled. Concrete walls have started..
Wylie High School Additions & Renovations
-
Area J Exterior Sheathing Complete. Concrete Bleacher work is done. Scaffolding set up for high ceiling work. MEP rough in near completion in locker/shower/office areas. Area K Interior Framing and MEP Overhead ongoing 1st floor. Area L 1st floor Slab on Metal Deck poured. Will be starting drywall framing and MEP overhead soon. Area D Overhead MEP ongoing. Drywall framing complete. Area V Finished Masonry. MEP rough in complete. Working on shower tile. Working on locker benches. Area C Tape Bed and Paint complete. Exterior awnings installed. Working on interior Trim Out
Bush Elementary Additions & Renovations
-
Area C Exterior waterproofing complete. Insulation panels are being installed. MEP rough ins are completed. Drywall complete. Tape and Bed has started. Freezer will be installed soon. HVAC equipment is scheduled to be installed next week. Area A Steel Erection is ongoing and nearly complete. Rebar has been installed for the North Wing 1st and 2nd Floor. Floor pours scheduled for the 2nd week in November including the Storm Shelter Floor. Floor Beams on south end of A complete. Metal Decking on 2nd Floor ongoing.
Cox Elementary Additions & Renovations
-
Area B Exterior
Installing Masonry face brick should be complete by middle of November. Final Layer of Roofing System ongoing should also be completed by middle of November. Exterior glazing complete.Area B Interior
MEP wall rough in completed. Drywall is completed. Tape and Bed should be complete by middle of November. Roll up door to be installed by November 16th. Duct insulation is complete above ceiling. Work on Storm Shelter panels ongoing. Main Switch Gear installed.
Watkins Elementary Additions & Renovations
-
Area A Cafeteria Exterior Framing complete. Sheathing on the north and east has started. Sheathing on the Parapet is near completion. Area A Gym Roof Decking is complete. HVAC Rough in has started under roof. Brick work has started on exterior.
Area E Storm Shelter Floor Decking is complete. Under Floor MEP rough in is complete. Roof Decking detailing is ongoing. Area E Classroom Waterproofing and flashing around windows is complete. Interior framing is complete. MEP rough in almost complete. Should be able to start two-siding drywall early November.
Harrison Intermediate Additions & Renovations
-
Area A Steel Erection is ongoing. Steel Decking on the 1st Floor is ongoing and should pour in the middle of November. Plumbing Rough ongoing in the Kitchen Area. The Roof Decking over the Kitchen Area is complete. Area B Exterior Waterproofing of the Storm Shelter in near completion. Parapet Framing is ongoing ahead of sheathing. Area B Interior Drywall Framing is nearly complete. Plumbing in wall rough in complete. HVAC Rough in ongoing.
Finished sod in track area and in parking at the front entrance should start planning trees 2nd week in November.