August 2020 Update Summary
-
The information below is a summary of the work done to date. For more detailed information, please view our monthly bond update document. The file contains several charts that may not be accessible to screen readers. If you need assistance with this information, please contact Nathan Watson, Director of Construction Services.
Wylie East High School Additions & Renovations
-
Area A Storm Shelter/Gym Structural Steel ongoing. MEP rough in continuing. The cafeteria expansion and the front classroom additions are complete and punch items ongoing. Front entry canopy work and landscaping in area is ongoing. Culinary Arts classroom is functional with punch items left to complete. Utilities and foundation work continued at areas D, L, M, R and the athletic areas to prepare for upcoming additions.
The cafeteria expansion and the front classroom additions are complete and working on finalizing punch items. Athletic areas has started foundation and underground utility work.
Wylie High School Additions & Renovations
-
Area J Roof decking is now complete. Nelson studs are being installed. MEP rough ins continue. Fire proofing ongoing. Area L Vertical steel has started. Floor beams are starting to be installed. Area D First Floor concrete slab on metal deck has been poured. MEP rough ins continue. Area V CMU load bearing walls at dug outs and tennis hut have started. Area C interior framing installed. MEP rough ins continue.
All interior renovation work complete and currently working on the punch.
Bush Elementary Additions & Renovations
-
Area C Roof decking complete. Floor decking complete. Should pour slab on metal deck for the floor soon followed by metal stud framing and MEP rough in.
Area A Half of walls for tornado shelter are poured should finish all the walls in the next two weeks. MEP under floor complete. Steel for flooring on Area B should begin in early September followed by installation of the vertical steel.
Cox Elementary Additions & Renovations
-
Area B All concrete walls poured. Grade beams have been waterproofed and backfilled. Roof decking in place. Under floor MEP rough in is ongoing. All sleeves at the roof and floor have been installed. Utility work is complete. Playground is complete.
In the coming weeks both the roof and the floor concrete should be poured. Metal framing of the parapet and exterior walls should start in late September..
Watkins Elementary Additions & Renovations
-
Area A masonry work ongoing between existing and new building. Area E Storm forms are being set for shelter walls. Area E Classrooms steel decking has been installed for both the roof and the floor.
In the coming weeks, the slab on metal deck should be poured in Area E classroom. CMU to continue going vertical. First section of concrete walls will be poured.
Harrison Intermediate Additions & Renovations
-
Area B Half the concrete walls are poured. MEP rough in is ongoing. Area A all the grade beams are complete. MEP underground rough in is ongoing. The track is complete still a little sod left to do on the filed which should happen this week.
In the coming weeks, the concrete will be completed in area B. Area A the structural steel should start for the slab on metal deck.
The summer one interior renovations are complete and currently finishing up the punch items.