August 2020 Update Summary

Wylie East High School Additions & Renovations

  • Area A Storm Shelter/Gym Structural Steel ongoing. MEP rough in continuing. The cafeteria expansion and the front classroom additions are complete and punch items ongoing. Front entry canopy work and landscaping in area is ongoing. Culinary Arts classroom is functional with punch items left to complete. Utilities and foundation work continued at areas D, L, M, R and the athletic areas to prepare for upcoming additions.

    The cafeteria expansion and the front classroom additions are complete and working on finalizing punch items. Athletic areas has started foundation and underground utility work.

    Wylie East High School Bond Construction Photo.  East side area. Wylie East High School Bond Construction Photo.  North East side area. Wylie East High School Bond Construction Photo.  South West side area. Wylie East High School Bond Construction Photo.  East Cafeteria area.

Wylie High School Additions & Renovations

  • Area J Roof decking is now complete. Nelson studs are being installed. MEP rough ins continue. Fire proofing ongoing. Area L Vertical steel has started. Floor beams are starting to be installed. Area D First Floor concrete slab on metal deck has been poured. MEP rough ins continue. Area V CMU load bearing walls at dug outs and tennis hut have started. Area C interior framing installed. MEP rough ins continue.

    All interior renovation work complete and currently working on the punch.

    Wylie High School Bond Construction Photo. South East side area.Wylie High School Bond Construction Photo. South East side area closer. Wylie High School Bond Construction Photo. South East aerial closer. Wylie High School Bond Construction Photo. South East aerial.

Bush Elementary Additions & Renovations

  • Area C Roof decking complete. Floor decking complete. Should pour slab on metal deck for the floor soon followed by metal stud framing and MEP rough in.

    Area A Half of walls for tornado shelter are poured should finish all the walls in the next two weeks. MEP under floor complete. Steel for flooring on Area B should begin in early September followed by installation of the vertical steel.

    Aerial photo of Bush Elementary School Aerial photo of Bush Elementary School Aerial photo of Bush Elementary School Aerial photo of Bush Elementary School

Cox Elementary Additions & Renovations

  • Area B All concrete walls poured. Grade beams have been waterproofed and backfilled. Roof decking in place. Under floor MEP rough in is ongoing. All sleeves at the roof and floor have been installed. Utility work is complete. Playground is complete.

    In the coming weeks both the roof and the floor concrete should be poured. Metal framing of the parapet and exterior walls should start in late September..

    Aerial photo of Cox Elementary School Aerial photo of Cox Elementary School Aerial photo of Cox Elementary School Aerial photo of Cox Elementary School

Watkins Elementary Additions & Renovations

  • Area A masonry work ongoing between existing and new building. Area E Storm forms are being set for shelter walls. Area E Classrooms steel decking has been installed for both the roof and the floor.

    In the coming weeks, the slab on metal deck should be poured in Area E classroom. CMU to continue going vertical. First section of concrete walls will be poured.

    Aerial photo of Watkins Elementary School Aerial photo of Watkins Elementary School Aerial photo of Watkins Elementary School Aerial photo of Watkins Elementary School

Harrison Intermediate Additions & Renovations

  • Area B Half the concrete walls are poured. MEP rough in is ongoing. Area A all the grade beams are complete. MEP underground rough in is ongoing. The track is complete still a little sod left to do on the filed which should happen this week.

    In the coming weeks, the concrete will be completed in area B. Area A the structural steel should start for the slab on metal deck.

    The summer one interior renovations are complete and currently finishing up the punch items.

    Aerial photo of Harrison Elementary School Aerial photo of Harrison Elementary School Aerial photo of Harrison Elementary School Aerial photo of Harrison Elementary School