June 2020 Update Summary
-
The information below is a summary of the work done to date. For more detailed information, please view our monthly bond update document. The file contains several charts that may not be accessible to screen readers. If you need assistance with this information, please contact Nathan Watson, Director of Construction Services.
Wylie East High School Additions & Renovations
-
Structural concrete storm shelter walls and slabs continued at area A along with structural steel. The cafeteria expansion and the front classroom additions continue to make progress towards completion. Interior finishes are underway, RTU’s have been started, masonry is ongoing, and the final roof sheets will be installed soon. Work on the front entry canopy has started and piers have been installed. MEP work is in progress in the Culinary Arts classroom and the vent hoods and wall tile have been installed. Utilities and foundation work continued at areas D, L, M, R and the athletic areas to prepare for upcoming additions.
The cafeteria expansion and the front classroom additions are scheduled to be complete in early August.
Wylie High School Additions & Renovations
-
Structural foundation work and the concrete storm shelter continued at the main addition with the placement of grade beams, storm shelter walls and lids. The structural steel installation is underway in area D and several floor slabs have been poured. The interior renovations of the Administration area and Auditorium is nearing completion with interior finishes underway. The handrail replacement made significant progress this month. The masonry walls have been installed at the Scene Shop and the ROTC marching area has been prepped for the new slab. Utilities and foundation work are underway on the baseball and softball dugouts and locker rooms.
All interior renovation work currently underway is scheduled to be complete in early August.
Bush Elementary Additions & Renovations
-
Site demolition and excavation are complete, most of the utility work is done and site grading is near complete. Subgrade prep was completed and the new areas of concrete for the bus entrance and the expanded front parking has been installed.
Piers will soon start for the building additions. Work will continue in the coming weeks to get the site ready for the start of school. This will include playground installation, fencing relocation, sidewalk installation and parking lot striping.
Cox Elementary Additions & Renovations
-
Most of the utility work, site grading and crawlspace excavation has been completed. The piers have been installed and grade beams are underway. Electricians and plumbers have also been working under the existing school to extend pathways to the new addition.
In the coming weeks, grade beams will continue, structural steel will be delivered and the installation of the floor will begin.
Watkins Elementary Additions & Renovations
-
Grading and utility work are underway. Building demo and site demo are complete. Electricians and plumbers have been working under the existing school to extend existing systems to the new addition. Crawlspace excavation is complete and piers have started at the additions. Work is underway in the administration area to make ready for the new reception desk.
Subgrade prep for site paving will start as soon as the utilities are completed. Piers will continue in the coming weeks, followed by grade beams and structural steel.
Harrison Intermediate Additions & Renovations
-
Site demolition and excavation are both complete and utility work is underway. Subgrade prep for paving has been approved and the installation of the new drive and parking areas have started. Piers have been installed and grade beam forms have started at the building additions. Interior renovations in area D are underway with new ductwork new ceiling grid already in place.
In the coming weeks, the paving will be complete, grade beams will continue followed by structural steel deliveries and the slab pour.
The interior spaces currently being renovated are scheduled to be complete in early August.