May 2020 Update Summary
-
The information below is a summary of the work done to date. For more detailed information, please view our monthly bond update document. The file contains several charts that may not be accessible to screen readers. If you need assistance with this information, please contact Nathan Watson, Director of Construction Services.
Wylie East High School Additions & Renovations
-
Structural concrete storm shelter walls continued at area A along with grade beams and structural steel. Significant progress was made at the cafeteria expansion and the front classroom additions. The building envelope system is nearing completion, fireproofing has been inspected, interior framing is in place, MEP rough-in is underway, and sheetrock is being installed. Interior renovations in the Culinary Arts classroom have started with demo complete and MEP work underway. The flooring has been removed from the Band area and new carpet is scheduled for June. Utilities and foundation work have started at areas D, L, M, R and the athletic areas to prepare for upcoming additions. The turn lane modification in Wylie East Drive is nearing completion.
All work listed above will continue throughout the month of June.
Wylie High School Additions & Renovations
-
Structural foundation work continued at the main addition with the placement of grade beams and concrete storm shelter walls. The structural steel is progressing and several floor slabs have been poured. The interior renovation of the administration area is well underway with demolition complete, walls framed, and most of the sheetrock in place. Auditorium finishes and preparation work for the new handrails is in progress. The slab is now in place at the scene shop addition and masonry walls will follow. Work has started on the baseball and softball dugouts and locker rooms with demolition complete and installation of piers underway.
All work listed above will continue throughout the month of June.
Bush Elementary Additions & Renovations
-
Work started in the second week of May. Pogue has set up their job trailer, installed staging areas, and put in the temporary fencing. Site demolition is nearing completion and utility work is underway. Excavation and site grading have begun and subgrade preparation for paving will start soon.
In the coming weeks, utilities, grading, and subgrade preparation for the paving will continue. Due to logistics and scheduling to allow access in the fall, building piers will commence after the front paving is installed.
Cox Elementary Additions & Renovations
-
Work started in the second week of May. Pogue has set up their job trailer and put in the temporary fencing. Site demolition is complete and utility work is underway. Excavation of the crawlspace is complete and site grading has begun. Electricians have also been working under the existing school to extend electrical pathways to the new addition.
In the coming weeks, utilities and MEP preparation will continue and the installation of the building piers will start.
Watkins Elementary Additions & Renovations
-
Work started in the second week of May. Cadence McShane has set up their job trailer, storage area, and put in the temporary fencing. Site demolition, grading, and utility work are underway. Building demolition has started at the cafeteria expansion. Electricians and plumbers have been working under the existing school to extend existing systems to the new addition.
Excavation of the crawlspace is set to start as soon as all utilities are rerouted and the building piers will follow. Subgrade preparation will start as soon as rough grading is complete then paving will be installed.
Harrison Intermediate Additions & Renovations
-
Work started in the second week of May. Pogue has set up their job trailer, installed staging areas, and put in the temporary fencing. Site demolition is nearing completion and utility work is underway. Excavation and site grading have begun and subgrade preparation for paving will start soon. Interior renovations have started with ceiling demolition in area D.
In the coming weeks, all work listed above will continue and subgrade prep for the paving will start. Building piers are scheduled to start by the third week of June.