December 2019 Update Summary
-
The information below is a summary of the work done to date. For more detailed information, please view our monthly bond update document. The file contains several charts that may not be accessible to screen readers. If you need assistance with this information, please contact Nathan Watson, Director of Construction Services.
Wylie East High School Additions & Renovations
-
Structural foundation work continues at areas A, E, H & K. Most of the structural building piers for the phase 1 additions have been installed and should be completed in early January. Grade beam forms are still underway at area A and the first set of beams have been poured. Grade beam excavation and forms have started at area H. The utility and main traffic drive rerouting is complete at the northeast corner of Area A. Oncor has installed the electrical feeders to the new transformer and the temporary power panels are in place.
Underground utilities and structural foundation work will continue in the coming weeks. Structural building piers should be complete in early January. Structural steel deliveries will start arriving in January.
Wylie High School Additions & Renovations
-
Excavation and haul off continued throughout the month with final grade being set at the main addition and area C. Structural foundation work has started at the main addition with approximately 10% of the piers installed and grade beam forms already underway. Utility work at the main addition and area C is nearing completion. The new grease trap has been installed and existing piping has been routed. During the break, investigation and preparations started for summer renovations. Various existing interior conditions were verified over the break and conduit racks for the first set of summer renovations were started.
Structural foundation work will continue into February and structural steel deliveries should start arriving in late January.
Phase 2 Additions & Renovations Bush, Cox, Watkins & Harrison
-
Our second phase of projects for the 2019 Bond consists of additions and renovations at Bush Elementary, Cox Elementary, Watkins Elementary & Harrison Intermediate. PBK has submitted the 95% progress set of construction documents for all four projects and the Construction Managers are working on updated budget estimates and constructability review comments that will help to further develop the construction documents. We should have final bid documents by mid-February 2020 and construction is expected to start in the Spring of 2020.