2009 Bond-BJHS Additions/Renovations | | Burnett Junior High School |
|
Click here for a virtual tour of needed renovations and additions. |  $8,202,000
The 2008 & Beyond Bond Committee recommended $8,202,000 in additions, renovations, and upgrades to Burnett Junior High School. Burnett Junior High School was originally constructed in 1975 as a 3A high school.
Additions & Renovations ($5,188,000) Renovations – Locker Rooms $1,208,000 Additional Locker Rooms/Dressing Area 1,908,000 Kitchen Additions & Renovations 1,034,000 Replace Gym Floors 222,000 Replace Flooring throughout Burnett 192,000 Classroom Renovations (Marker Boards) 64,000 Choir Room Addition 530,000 Upgrades in Main Gym 30,000
Infrastructure Upgrades ($3,014,000) Electrical Upgrades $878,000 Gymnasium Lighting Upgrades 38,000 Computer Room HVAC 45,000 Replace Public Address System 219,000 Roof Replacement 1,382,000 Fire Sprinkler System 439,000 Computer Room Upgrades 13,000
|